BayOfBengal Nov15 * SG171 * Dive index * Mission links
Based on low voltage useage over previous 10 dives:
    dives remaining   : -35 (-7.4 days at current dive duration)
    projected end date: 01-Feb-2016 20:07:53 (to 15% capacity)

Based on high voltage useage over previous 10 dives:
    dives remaining   : 536 (113.8 days at current dive duration)
    projected end date: 02-Jun-2016 01:19:44 (to 15% capacity)

High voltage pack usage


Low voltage pack usage